Abstract

PT Pertamina TBBM Tanjung Priok - Plumpang is one of the downstream oil facilities that plays an important role in the distribution and distribution of fuel for the community. Because, about 20% of the daily fuel needs in Indonesia are supplied from TBBM Tanjung Priok - Plumpang owned by PT Pertamina (Persero). In the course of time, many incidents (fire, etc.) within the scope of TBBM Plumpang. Therefore, this research aims to examine the application of Risk Management in the company PT Pertamina TBBM Tanjung Priok - Plumpang. This research uses a qualitative approach conducted through a process of interviews and direct observation. The purpose of applying Risk Management to this company is to identify what risks are involved in Risk Management within the scope of PT Pertamina TBBM Tanjung Priok-Plumpang by measuring the risk of probability and impact, and evaluating each existing risk, according to the case study of Tank X construction within the Tanjung Priok TBBM area. This research is expected to assist management in taking actions and responses to reduce the negative impacts of the possibilities that will occur in the future and provide an assessment of the various risks that exist. The results of this study will contain risk classes ranging from high risk, medium risk, and low risk.

Keywords: Risk Management, Non – Financial Performance, Risk, Impact

 

 

Introduction

The fire case at PT Pertamina Plumpang Depot was shocking and saddening for the people of Indonesia. When viewed from the outside, security issues and safety SOPs at PT Pertamina Plumpang itself are very strict. However, with the reason for the cause of the fire which was analyzed from several sources that with the occurrence of technical disturbances that resulted in excessive pressure so that the fire occurred (Wirandaru, 2023). However, from other sources, the cause of the fire at the Plumpang depot came from the fuel inlet pipe, which is located close to the residential parapet. Pertamina's depot, which is one of the most important fuel terminals in Indonesia and is world-class, has also experienced a fire in 2009, which resulted in losses of around 17 billion. After the incident, Vice President Jusuf Kalla asked PT Pertamina (Persero) to maintain security and safety standards at the oil refinery (Yakub & Phuspa, 2019).

The experience of the above events leads to the conclusion that even though reports and checks are routinely issued, it does not mean that a company is free from risks. In today's global era, attention to risk assessment is fundamental. This is because in the global area, businesses are faced with an environment of very high uncertainty and complexity (Aditya & Naomi, 2017). Moreover, as we know PT Pertamina Persero is a company engaged in the oil and gas sector, so it must pay attention to occupational health and safety (Health & Safety) which is a significant problem and an important factor in determining excellence for competitiveness and must require serious attention and management of efforts in the field of occupational health and safety.

PT Pertamina (Persero) is one of the leading national oil companies in Indonesia that plays an important role in the distribution and procurement of oil and gas resources in Indonesia. In this effort, of course, facilities are needed to store and distribute these products so that people can utilize energy in meeting their needs. The Fuel Oil Depot (BBM) in Priuk, North Jakarta is one of the terminals owned by PT Pertamina Patra Niaga as one of the entities of PT Pertamina (Persero) which holds responsibility for storing and distributing production.  The place commonly used to store petroleum products is a tank. Tanks in the oil and gas industry are structures that are used as storage for crude oil, LNG, and their derivative products including fuel oil (BBM). In general, the oil storage tank or liquid material is in the form of a cylinder which has a large enough diameter.  The activities of PT Pertamina Persero involve all aspects of the field, from upstream to downstream. In accordance with Pertamina's aspirations to become a Global Energy Champion with a market value of US $ 100 billion, of course, it must increase PT Pertamina's consistency in the implementation of ESG (Environmental, Social & Governance) aspects, especially those related to social aspects where occupational health and safety are the main concerns, namely by providing appropriate responses to risks that may occur. Of course, this is done with the aim of minimizing the risk costs that will be incurred and increasing company profits, increasing employee productivity and loyalty and for the sake of maintaining the company's image in the eyes (international world). The research aims to examine the application of Risk Management in the company PT Pertamina TBBM Tanjung Priok - Plumpang.

 

Research Methods

This research uses a qualitative method with a descriptive approach (Creswell & Creswell, 2017). In this study using qualitative methods where the results of the analysis are in the form of analysis of each existing risk. This research uses the following data collection methods:

Observation Technique

In this observation technique, information is recorded when making observations in the field, precisely on the X tank Upgrading project. This observation is carried out for later interviews/discussions together with the contractor or owner. Observations in the field also sometimes coincide with interview techniques where if at the time of observation there are things that are not understood, then questions and answers are asked with the contractor or owner. This observation is also carried out if there is data that cannot be obtained through interviews. Observation is also carried out to better understand technical matters related to the project so that it makes it easier to analyze.

Documents

In this study, document techniques were used where in this study documents were obtained in the form of Project TOR, technical drawings, material approval letters obtained from the contractor. These data are needed for the analysis needs in this study which can be accounted for because they have gone through the approval process.

Interview

In this research, interview techniques were also carried out where discussions were held with the executor in this case the contractor and owner. This interview was conducted based on the results of observations and project documents or other documents mentioned in the previous section. Information from the interview results is used as an addition to the analysis carried out.

 

Figure 1. Flowchart

 

Results and Discussion

The risk analysis process involves observing the job site to obtain an initial risk identification, and then analyzing it with a probability and impact matrix. This risk identification is an iterative process where risks sometimes arise during project implementation or throughout the project life cycle. Based on PMBOK edition 6, this risk analysis is both qualitative and quantitative (Stackpole, 2013). Qualitatively, a risk prioritization analysis process is carried out to be followed up with an assessment that can show the likelihood of risk occurrence and its impact (Tavan & Hosseini, 2016). While quantitative is a numerical analysis which is a combination of risk identification. The table below shows the results of the risk management analysis on the oil tank lifting process that has been adjusted to the assessment provisions in table 1.

 

Table 1. Hazard Table

NO

Type Of Event

Potential Hazards

Consequences

Consequences

Intial Risk

Safeguards (Existing and Recommended Control Measures)

Consequences

Residual Risk

People

Asset

Environment

Reputation

S

L

R

People

Asset

Environment

Reputation

S

L

R

1

Crawler crane installation

Soil cannot bear the weight of the crawler crane

Crane has decreased so that when lifting the tank it is unstable until it rolls over

Multiple fatalities

Extensive damage

Local effect

International impact

4

3

High

Testing the compressive strength of the soil to determine the strength of the soil in holding the load on it

Minor injury

Local damage

Local effect

Major impact

3

3

Low

tilt crawler crane

Load fell and caused damage to equipment and tank

Multiple fatalities

Extensive damage

Local effect

International impact

4

3

High

The use of cranes must be in accordance with the capacity requirements that have been multiplied by the safety factor so that it is safer to hold the tank.

Minor injury

Local damage

Local effect

Major impact

3

2

Low

Crane installation must be in accordance with the worker's briefing and signage.

Use PPE to reduce the risk of injury to workers

Conduct a re-briefing on OHS to reduce the risk of the same accident recurring.

Physical injury and loss of life if the tank falls or rolls over

Multiple fatalities

Major damage

Local effect

International impact

5

3

High

Complete use of PPE in accordance with the standards where the project is carried out so as to reduce the risk of fatal injuries.

Minor injury

Local damage

Local effect

Major impact

3

2

Low

Loss in terms of budget and loss in terms of time

Major injury

Extensive damage

Local effect

International impact

5

3

High

Work with good concentration and focus so that there is less risk of human error when operating the crane.

Minor injury

Local damage

Local effect

Major impact

3

2

Low

Re-briefing on OHS to prevent the same accident from occurring.

 

Full PPE is used to reduce the risk of fatal injury.

Mast fall

Physical injury and loss of life if the tank falls or rolls over

Fatality

Major damage

Local effect

National impact

4

3

Medium

Work with good concentration and focus so that there is less risk of human error when operating the crane.

Minor injury

Minor damage

Minor effect

Limited impact

2

2

Low

Re-briefing on OHS to prevent the same accident from occurring.

Briefing on OHS is conducted again to reduce the occurrence of the same incident

Loss in terms of budget and loss in terms of time

No/slight injury

Major damage

Minor effect

National impact

3

3

Medium

Use full PPE to reduce the risk of injury.

No/slight injury

Minor damage

Minor effect

Limited impact

2

2

Low

Work with good concentration and focus so that there is less risk of human error when operating the crane.

The tank becomes unbalanced and may cause the tank to topple over

Multiple fatalities

Extensive damage

Major effect

National impact

5

3

High

Crane operators must be certified so that operations can be carried out properly.

Minor injury

Minor damage

Local effect

Limited impact

2

3

Low

Use full PPE to avoid injury.

Worker slips during crane installation

Workers suffer fatal injuries and death

Minor injury

No/Slight damage

Minor effect

Minor impact

2

3

Low

Full PPE is used to reduce the risk of fatal injury.

No/slight injury

No/Slight damage

Minor effect

Limited impact

2

2

Low

Work with good concentration and focus so that there is less risk of human error when operating the crane.

Work was temporarily suspended due to an accident

Minor injury

No/Slight damage

Minor effect

Minor impact

2

3

Low

Conduct a re-briefing on OHS to reduce the risk of the same accident recurring.

No/slight injury

No/Slight damage

Minor effect

Limited impact

2

2

Low

Jib broke due to overload

Workers suffer fatal injuries and death

Fatality

Major damage

Local effect

National impact

4

3

Medium

Full PPE is used to reduce the risk of fatal injury.

Minor injury

Minor damage

Minor effect

Limited impact

2

2

Low

Workers are certified so they can operate the crane properly.

Operators follow directions and job signs

Work with good concentration and focus so that there is less risk of human error when operating the crane.

Loss in terms of budget and loss in terms of time because the project is temporarily suspended

No/slight injury

Major damage

Minor effect

National impact

3

3

Medium

Re-direction of K3 is carried out as an effort to avoid the re-occurrence of the same accident.

No/slight injury

Minor damage

Minor effect

Limited impact

2

2

Low

Damage to tools

No/slight injury

Major damage

Minor effect

National impact

3

3

Medium

Conduct a re-briefing on OHS to reduce the risk of the same accident recurring.

No/slight injury

Minor damage

Minor effect

Limited impact

2

2

Low

 

 

An earthquake occurred during crane operation

damage to tanks near tank 22

Minor injury

Local damage

Minor effect

Major impact

3

3

Medium

Operators who operate cranes must be certified to avoid a high risk of accidents.

Minor injury

Minor damage

Minor effect

Limited impact

2

3

Low

Analyze whether the structure is strong against earthquakes or to maintain the balance of the tank in the event of an earthquake.

Workers suffer fatal injuries and death

Fatality

Major damage

Local effect

National impact

4

3

Medium

Full PPE is used to reduce the risk of fatal injuries.

Minor injury

Minor damage

Minor effect

Limited impact

2

2

Low

Stay focused while working to avoid fatal injuries if the tank topples over during an earthquake

Evacuate or give first aid to accident victims.

Damage to other facilities near the tank 22

Fatality

Major damage

Major effect

National impact

3

3

Medium

Analyze whether the structure is strong against earthquakes or to maintain the balance of the tank in the event of an earthquake.

Major injury

Local damage

Minor effect

Major impact

2

3

Low

Stopping activities at the entire Tanjung Priok TBBM Installation due to accidental falling loads to avoid other risks that cause huge losses in terms of profit and also in terms of production or distribution.

Fatality

Major damage

Major effect

National impact

3

4

High

The analysis is carried out first to get the balance of the tank in the event of an earthquake so that there is no overturning of the tank due to an earthquake or overturning of the crane.

Major injury

Local damage

Minor effect

Major impact

2

3

Low

Crane toppled over and the load also toppled over

Workers suffered fatal injuries and even death

Fatality

Major damage

Local effect

National impact

4

3

Medium

Full PPE is used to reduce the risk of fatal injuries.

Minor injury

Minor damage

Minor effect

Limited impact

2

2

Low

Stay focused while working to avoid fatal injuries if the tank topples over during an earthquake

Perform evacuation or first aid on accident victims

During sleewing, the crane hits the worker or another tank.

damage to other facilities at TBBM

Fatality

Major damage

Major effect

National impact

3

3

Medium

Operators who operate cranes must be certified to avoid accidents.

Major injury

Local damage

Minor effect

Major impact

2

3

Low

Must stay focused while doing work so as to avoid accidents.

Workers are injured to the point of permanent disability or death.

Fatality

Major damage

Major effect

Major impact

3

3

Medium

Full PPE is used to reduce the risk of fatal injuries.

Major injury

Local damage

Minor effect

Major impact

2

3

Low

Stay focused while working to avoid fatal injuries if the tank topples over during an earthquake

Perform evacuation or first aid on accident victims

Patahan Jib mengenai pekerja

Fatality

Local damage

Minor effect

Major impact

4

3

Medium

Use PPE to reduce the risk of injury to workers

Minor injury

Minor damage

Minor effect

Limited impact

2

3

Low

Stay concentrated while working to avoid being thrown by a broken Jib

Crane suffers engine failure

Work was temporarily halted resulting in losses in terms of time and cost

No/slight injury

Local damage

No/Slight effect

Major impact

3

3

Medium

Regular maintenance is carried out to ensure that the crane is in optimum or good condition when operating.

No/slight injury

Minor damage

No/Slight effect

Limited impact

2

3

Low

Crane overturned due to overload

The load rolled along with the crane, which could hit other facilities at the TBBM and incur cost losses.

Fatality

Major damage

Major effect

National impact

3

3

Medium

Well analyzed for crane capacity calculation to avoid crane overload.

Major injury

Local damage

Minor effect

Major impact

2

3

Low

When analyzing the crane capacity, it has been multiplied by the safety factor.

Workers are injured to the point of permanent disability or death.

Fatality

Major damage

Major effect

Major impact

3

3

Medium

Workers must remain focused while doing their work because if an accident occurs, workers can avoid it more quickly. Workers are also required to use complete PPE in accordance with applicable regulations. In the event of a victim, immediately provide help as early as possible.

Major injury

Local damage

Minor effect

Major impact

2

3

Low

There was a collision between cranes

Damage to equipment and other facilities at TBBM

Fatality

Major damage

Major effect

Major impact

3

3

Medium

Operators who operate cranes must be certified to avoid errors in operation. At the time of operation must follow the signs of work at the project site. Continue to use PPE in accordance with applicable standards. provide immediate first aid if there are accident victims.

Major injury

Local damage

Minor effect

Major impact

2

3

Low

Time and cost losses due to crane collision accidents

No/slight injury

Local damage

No/Slight effect

Major impact

3

3

Medium

Operators who operate cranes must be certified to avoid errors in operation. At the time of operation must follow the signs of work at the project site.

No/slight injury

Minor damage

No/Slight effect

Limited impact

2

3

Low

Injury to crane operator or injury to workers

Fatality

Major damage

Major effect

Major impact

3

3

Medium

Use PPE in accordance with applicable standards and stay focused while working. Immediately perform first aid in the event of an accident victim

Major injury

Local damage

Minor effect

Major impact

2

3

Low

Crane on fire

Equipment damaged by fire

Minor injury

Major damage

Minor effect

National impact

3

3

Medium

Cranes must be maintained according to the schedule and not skip any part of the check during maintenance. Crane operations must be carried out by professional and certified operators.

No/slight injury

Minor damage

Minor effect

Limited impact

2

2

Low

Workers are injured to death

Fatality

Major damage

Major effect

Major impact

3

3

Medium

Workers or operators must comply with regulations regarding K3 at the project site and continue to use PPE in accordance with applicable standards, if there are victims then immediately provide assistance.

Major injury

Local damage

Minor effect

Major impact

2

3

Low

There are disadvantages in terms of cost and in terms of time

No/slight injury

Local damage

No/Slight effect

Major impact

3

3

Medium

Workers or operators must comply with regulations regarding K3 at the project site and continue to use PPE in accordance with applicable standards, if there are victims then immediately provide assistance.

No/slight injury

Minor damage

No/Slight effect

Limited impact

2

3

Low

Unsafe crane height

Crane terguling

Fatality

Major damage

Major effect

Major impact

3

3

Medium

Crane operation must be in accordance with the standard or initial design that has been planned and has been calculated and analyzed to avoid accidents. Operators who operate the crane must be professional and certified so that they can operate the crane properly.

Major injury

Local damage

Minor effect

Major impact

2

3

Low

Crane has broken

Fatality

Major damage

Major effect

Major impact

3

3

Medium

Crane operation must be in accordance with the standard or initial design that has been planned and has been calculated and analyzed to avoid accidents. Operators who operate the crane must be professional and certified so that they can operate the crane properly.

Major injury

Local damage

Minor effect

Major impact

2

3

Low

Dropped or rolled loads

Multiple fatalities

Extensive damage

Major effect

National impact

5

3

High

Crane operation must be in accordance with the standard or initial design that has been planned and has been calculated and analyzed to avoid accidents.

Minor injury

Minor damage

Local effect

Limited impact

2

3

Low

Injury to workers or death

Fatality

Major damage

Major effect

Major impact

3

3

Medium

Continue to use complete PPE when working and comply with other OHS requirements when at the project site. In the event of an accident victim immediately perform first aid.

Major injury

Local damage

Minor effect

Major impact

2

3

Low

Workers breathe in a lot of dust when cleaning crawler cranes

Workers experience oxygen deprivation and workers experience shortness of breath and respiratory infections.

Fatality

Major damage

Major effect

Major impact

3

3

Medium

Workers use dust masks when working in locations that produce a lot of dust. Workers use complete PPE and comply with other OHS at the project site. Immediately provide assistance if there are victims

Major injury

Local damage

Minor effect

Major impact

2

3

Low

Workers temporarily or permanently disabled due to respiratory infection

Major injury

Major damage

Major effect

Major impact

3

3

Medium

Workers use dust masks when working in locations that produce a lot of dust. Workers use complete PPE and comply with other OHS at the project site. Immediately provide assistance if there are victims to reduce the risk of disability.

Major injury

Local damage

Minor effect

Major impact

2

3

Low

Terjadi human eror pada saat pengoprasian boom

Posisi boom berubah dan berakibat fatal karena beban terguling

Multiple fatalities

Extensive damage

Major effect

National impact

5

3

High

Operator yang mengoprasikan crane haruslah telah bersertifikasi dan fokus saat bekerja. Pengoprasian harus sesuai dengan standar awal yang telah direncanakan. Gunakan APD lengkap untuk mengurangi resiko cidera parah apabila accident terjadi.

Minor injury

Minor damage

Local effect

Limited impact

2

3

Low

Boom broken

Multiple fatalities

Extensive damage

Major effect

National impact

5

3

High

Operators who operate the crane must be certified and focused when working. The operation must be in accordance with the initial standards that have been planned. Use complete PPE to reduce the risk of severe injury if an accident occurs and immediately provide assistance if there are victims.

Minor injury

Minor damage

Local effect

Limited impact

2

3

Low

Loss on costs due to temporary stoppage of the project

No/slight injury

Local damage

No/Slight effect

Major impact

3

3

Medium

Workers or operators must comply with regulations regarding OHS at the project site and continue to use PPE in accordance with applicable standards, if there are victims then immediately provide assistance. Operators who operate must be professional and certified.

No/slight injury

Minor damage

No/Slight effect

Limited impact

2

3

Low

Injury to workers until death or Disability to workers or crane operators

Major injury

Major damage

Major effect

Major impact

 

 

3

3

Medium

Use complete PPE to reduce the risk of severe injury if an accident occurs and immediately provide assistance if there are victims.

Major injury

Local damage

Minor effect

Major impact

2

3

Low

Hoist experienced an error due to incorrect operation

Load is unstable or even toppled over

Multiple fatalities

Extensive damage

Major effect

National impact

5

3

High

Operators who operate the crane must be certified and focused when working. The operation must be in accordance with the initial standards that have been planned. Use complete PPE to reduce the risk of severe injury if an accident occurs and immediately provide assistance if there are victims.

Minor injury

Minor damage

Local effect

Limited impact

2

3

Low

Damage to other TBBM facilities resulting in heavy losses in terms of costs

Fatality

Major damage

Major effect

Major impact

3

3

Medium

Operators who operate cranes must be certified to avoid errors in operation. At the time of operation must follow the signs of work at the project site. Immediately stop other activities around the project to avoid bigger accidents due to damage to facilities.

Major injury

Local damage

Minor effect

Major impact

2

3

Low

Workers suffered permanent injuries and even died

Fatality

Major damage

Major effect

Major impact

3

3

Medium

Workers or operators must comply with regulations regarding K3 at the project site and continue to use PPE in accordance with applicable standards, if there are victims then immediately provide assistance.

Major injury

Local damage

Minor effect

Major impact

2

3

Low

3

Maintenance crane

Worker hit by key tools for crane maintenance

Workers experience fatal injuries that cause permanent disability to death due to accidents and work is temporarily stopped so that they experience losses in time and costs.

Fatality

Major damage

Major effect

Major impact

3

3

Medium

Workers or operators must comply with regulations regarding K3 at the project site and continue to use PPE in accordance with applicable standards, if there are victims then immediately provide assistance.

Major injury

Local damage

Minor effect

Major impact

2

3

Low

Worker electrocuted during maintenance

Workers suffer permanent physical injuries and even death

Fatality

Major damage

Major effect

Major impact

3

3

Medium

Workers remain focused while performing work and use PPE in full accordance with regulations. Workers obey the work signs on the project and comply with other OHS regulations that apply on the project.

Major injury

Local damage

Minor effect

Major impact

2

3

Low

The mentality of other workers was shaken by the accident.

Major injury

Major damage

Major effect

Major impact

3

3

Medium

Immediately evacuate the victim and provide immediate assistance to reduce the risk of severe injury and affect other workers. Conduct a re-briefing on OHS on the project after an accident occurs.

Major injury

Local damage

Minor effect

Major impact

2

3

Low

Time and cost losses due to temporary project stoppages

Fatality

Major damage

Major effect

Major impact

3

3

Medium

Workers or operators must comply with regulations regarding K3 at the project site and continue to use PPE in accordance with applicable standards, if there are victims then immediately provide assistance.

Major injury

Local damage

Minor effect

Major impact

2

3

Low

4

Crane unloading

Worker falls while dismantling crane

Workers suffer permanent physical injuries and even death

Fatality

Major damage

Major effect

Major impact

3

3

Medium

Workers or operators must comply with regulations regarding OHS at the project site and continue to use PPE in accordance with applicable standards, if there are victims then immediately provide assistance. Workers comply with existing work signs on the project. Conduct a re-briefing on OHS if an accident occurs to avoid the same accident from happening again.

Major injury

Local damage

Minor effect

Major impact

2

3

Low

Project was temporarily suspended and incurred cost losses

Fatality

Major damage

Major effect

Major impact

3

3

Medium

Workers or operators must comply with regulations regarding K3 at the project site and continue to use PPE in accordance with applicable standards, if there are victims then immediately provide assistance.

Major injury

Local damage

Minor effect

Major impact

2

3

Low

Additional counterwight fell during operation

Damage to other facilities at TBBM

Fatality

Major damage

Major effect

Major impact

3

3

Medium

Workers or operators must comply with regulations regarding K3 at the project site and continue to use PPE in accordance with applicable standards, if there are victims then immediately provide assistance. Operation must be in accordance with the planned standards..

Major injury

Local damage

Minor effect

Major impact

2

3

Low

Workers suffer semi-permanent to permanent injuries or workers die

Fatality

Major damage

Major effect

Major impact

3

3

Medium

Immediately evacuate the victim and provide immediate assistance to reduce the risk of severe injury and affect other workers. Conduct a re-briefing on OHS on the project after an accident occurs.

Major injury

Local damage

Minor effect

Major impact

2

3

Low

 

From the results of the analysis in the table above, namely the hazards of the tangka lifting process in the tangka X construction project at TBBM Tanjung Priok, several medium and high value risks were found. The risk assessment in this analysis process is in accordance with the existing assessment requirements. This risk identification is carried out to anticipate problems on the project and analyze the actions that must be taken if the risk occurs, so that if in the process of running the project the risk occurs it will not have too much impact. The risks identified in the table above are high-value risks that must be prevented as well as possible. From the analysis results, there are 8 risks that can occur on the project. Risk management guidelines should be made with the aim of being easy to understand and understand so that the application in the field can run optimally.

 

Conclusion

The implementation of Risk Management helps companies to manage risks well where the risks are identified and assessed. In the risk analysis, there are 8 risks that can occur in the project which are considered to have a high risk impact. From the analysis results, there are 5 risks with moderate levels and 3 risks that are of high value. Using the application of PMBOK in risk analysis can make risk management guidelines easier to understand and understand but still detailed in the analysis process which can help smooth the project being implemented. Therefore, the application of the Project Management Body of Knowledge in the project world is very calculated. Because as we know PMBOK can help to plan, organize, and improve from every aspect within the scope of the world of construction projects. There are 4 ways used, namely rejecting (avoid), reducing (reduce), accepting (accept), and sharing (share). Mostly, companies take action to reduce risks to reduce the negative impact arising from these risks.  The implementation of Risk Management can help companies to improve non-financial performance where the main goal is to meet consumer needs. By measuring the existing risks, the company will know whether the existing risks are classified as high / medium / low risk and then the company will be able to manage risks based on their priority level first.

 

 

BIBLIOGRAPHY

 

Aditya, O., & Naomi, P. (2017). Penerapan manajemen risiko perusahaan dan nilai perusahaan di sektor konstruksi dan properti. Esensi: Jurnal Bisnis Dan Manajemen, 7(2), 167–180.

Airmic, A., & IRM, A. (2002). A risk management standard. AIRMIC, ALARM, IRM.

Boulton, R., Libert, B., & Samek, S. (2000). Cracking the Value Code: How Successful Businesses are Creating Wealth in the Economy. Wiley.

Boynton, W. C., & Johnson, R. N. (2005). Modern auditing: Assurance services and the integrity of financial reporting. John Wiley & Sons.

Brett, J., Green, D., & Moran, A. (2011). Managing risk in community services: a preliminary study of the impacts of risk management on Victorian services and clients.

Creswell, J. W., & Creswell, J. D. (2017). Research design: Qualitative, quantitative, and mixed methods approaches. Sage publications.

Firgianto, P., & Djati, S. P. (2020). Analisis Risiko Pengadaan Tanah Untuk Eksplorasi dan Eksploitasi Minyak dan Gas Bumi (Studi Kasus: PT. Pertamina EP-Paku Gajah Development Project). Jurnal Manajemen Risiko1(1), 93-126.

Luri, H., & Rinawati, D. I. (2019). Analisis Risiko Keselamatan dan Kesehatan Kerja Dengan Menggunakan Job Hazard Analysis (Studi Kasus Pt. Pertamina Ep Asset 4 Field Cepu). Industrial Engineering Online Journal8(1).

Stackpole, C. S. (2013). A User’s Manual to the PMBOK Guide. John Wiley & Sons.

Tavan, F., & Hosseini, M. (2016). Comparison and analysis of PMBOK 2013 and ISO 21500. Journal of Project Management, 1(1), 27–34.

Wirandaru, A. (2023). Konstruksi Realitas Pemberitaan Kebakaran Depo Pertamina Plumpang pada Tayangan Berita Youtube Kompas TV Periode 07-09 Maret 2023.(Construction Reality Reporting of The Pertamina Plumpang Storage Fire on Kompas TV Youtube News Shows For The Period Of 07-09 March 2023). Universitas 17 Agustus 1945 Surabaya.

Wibowo, A. A. (2019). Analisa risiko keselamatan kerja pada explorasi minyak. Jurnal Baut dan Manufaktur1(1), 57-68.

Yakub, M., & Phuspa, S. M. (2019). Manajemen Risiko Kebakaran pada PT Pertamina EP Asset 4 Field Sukowati. J Ind Hyg Occup Heal, 3.

 

 

Copyright holder:

M. Fanshurullah Asa, Yessy Rama Natalia Pakpahan, Okfi Risa Sabila (2024)

 

First publication right:

Syntax Literate: Jurnal Ilmiah Indonesia

 

This article is licensed under: