Syntax Literate: Jurnal Ilmiah Indonesia p�ISSN:
2541-0849 e-ISSN: 2548-1398
Vol. 7, No. 6, Juni 2022
RISK COST-BENEFIT
ANALYSIS OF 3 GI ANGKE TRANSFORMERS TO ACHIEVE OPTIMAL MITIGATION
Imran Syahrizal, Budi Sudiarto
Engineering Faculty University of
Indonesia Depok, Indonesia
Email: [email protected],
[email protected]
Abstract
The
power transformer is one of the leading electrical instruments used to transmit
electrical power between generators to adjust the voltage without changing its
frequency. Like any other machine, the power transformer will experience
degradation over time. High electrical resistance, external factors and
environmental temperature could lead to faster degradation. This degradation
usually affects transformer isolation material. Degradation of this component
furthermore will decrease power transformer efficiency. In 2022, power
transformer 3 GI Angke has been used for 28 years,
while PT PLN (Persero) has decided that power transformers operating for over
25 years fall into the category of the old machine and need to be replaced. The
last asset wellness maintenance data showed that ethane was found in the oil
insulation in the second level inspection. The third level inspection also
showed degradation of bushing insulation, with the tan delta test result
showing the value of 1.28. Asset wellness management is needed in this
situation to ensure stability. There are two mitigation options available, to
replace some of the components or replace the power transformer altogether. Risk,
cost and benefit analysis using a multicriteria approach is used in choosing
the best mitigation approach for PT PLN (Persero).
Keywords: asset management, power transformer, multi-criteria analysis
Introduction
PT PLN (Persero) is responsible for supplying
electricity for all customers. Electricity is generated from the generator
through transmission and distribution lines so that customers can use the
electricity. One of the vital components of the electricity distribution system
is the power transformer. To maintain stable service, power transformers with
an operating age of over 25 years are included in the old category according to
PLN's SK DIR 149.
One of the transformers managed by PLN is
transformer three at GI Angke. This transformer is 28
years old. Based on the last test results, an assessment of the Health Index of
the transformer was carried out.
Determination of equipment health index using logic OR
Table 1. Classification Of 1,6, 9 For Each Inspection Item.
No |
Sub System |
Item Inspection |
Test Result |
Score Item Inspection |
Score Subsystem |
Score Health Index |
1 |
Dielectric |
DGA |
548.21 (4) |
1 |
1 |
|
2 |
Current Carrying unit |
Tan Delta |
1.63 % |
1 |
1 |
1 |
3 |
Bushing |
Tan Delta |
1.38 % |
1 |
1 |
|
Based on table 1, the health index of the 3 GI Angke transformer is 1. Moreover, the susceptibility of the 3 GI Angke transformer is determined using the data below.
Table 2
Susceptibility Simulation Scoring Results.
No |
Parameter Susceptibility |
Score |
Index |
Average |
Susceptibility |
1 |
Average loading (1 year) |
79.6 % |
6 |
28/5 =5.5 |
6 |
2 |
TFC |
270100 |
6 |
||
3 |
Neutral |
12 ohms |
6 |
||
4 |
Life |
>25 |
1 |
||
5 |
load type |
Linear |
9 |
Based on table 2, the susceptibility of the transformer 3 GI Angke = 6
Figure 1. The Risk Assessment Matrix
�����������
Following the health index score = 1 and the
susceptibility score = 6, using the matrix above, the probability of failure
3 GI transformer Angke = DIn
order to determine the priority of work, the probability of failure is combined
with the GI criticality. Transformer #3 GI Angke has
a criticality level of 4, so based on the matrix below, the priority of work on
transformer #3 GI Angke is priority 1 (red).
Figure 2. Matrix For Determining The
Priority
An old Power Transformer is very susceptible to
failure due to a decrease in the quality of insulation or damage to its components.
To minimize interference, the old transformer can be taken corrective action.
Actions that can be taken care in the form of replacing a new transformer or
repairing damaged components. Each mitigation action has its advantages and
disadvantages. For this reason, it is necessary to analyze
the costs/benefits and risks of the two mitigation action options. Limited
resources and time owned by PT PLN (Persero) are essential considerations in
determining mitigation actions with the most optimal benefits.
Cost analysis is related to the investment costs
required in mitigation actions. Risk analysis includes the calculation of
machine usability and customer satisfaction. In comparison, the benefit
analysis calculates the efficiency of the machine and the company's profits.
These three factors are summarized into the following 5 criteria, which are
used as considerations in selecting mitigation actions, including:
1.
% Transformer Readiness
% transformer
readiness is the percentage of transformer readiness in delivering electrical
power to its nameplate capacity. A decrease in % transformer readiness occurs
if the results of the transformer assessment show deterioration. The assessment
parameters used in the loading reference are DGA test assessments, oil characteristics
and electrical tests. In this journal, % transformer readiness is divided into
3 with the distribution of values:
2: declaration of % transformer readiness
>90%
1: 80 % < declaration of % readiness transformer
< 90%
0: declaration % transformer readiness < 80%
2.
Power Transformer Life
Transformer life is when
the transformer can operate since it is first energized. The longer the
transformer can operate, the better for PT PLN (Persero) due to the large
investment costs for new transformer installations starting from the
procurement of transformers until the transformer can finally be energized.
Transformer life is grouped into 3 value categories:
2: lifetime >15 years
1: lifetime 5-15 years
0: lifetime <5 years
3.
Investment cost
The number of investment
costs causes stakeholders to consider the available options in dealing with the
case of a transformer that has deteriorated. This is important because PT PLN
(Persero) manages GIs throughout Indonesia, where each GI has its transformer
problem. Investment costs are also categorized into 3 value groups:
2: investment costs<1M
1: investment costs 1-10M
0: investment costs >10M
4.
Rupiah ENS (Energy Not
Served)
The reliability of a
transformer can be seen from the frequency and duration of the transformer
experiencing disturbances. One of the indicators used is the ENS transformer.
This ENS is used to determine the number of losses experienced by PT PLN
(Persero) due to the transformer not operating due to interference. The amount
of ENS rupiah is categorized into 3 values:
2: ENS Rupiah = IDR 0, -
1: ENS Rupiah = IDR 0, - to IDR 86, 820, 000, -
0: ENS Rupiah > 86, 820, 000, -
5.
Level of customer
satisfaction
Apart from pursuing
profit, PT PLN (Persero) as a BUMN must also pay attention to customer
satisfaction. The level of customer satisfaction can be seen through the level
of voltage and frequency that reaches the customer's house line, the number of
power outages and customer complaint reports. The level of customer satisfaction
is grouped into 3 values:
2: nominal voltage
1: voltage drop
0: complaints occur
Each value of the 5 criteria above is used to
compare the two available mitigation actions.
Table 3
Criteria for comparing mitigation options
|
Value |
||
Criterion |
2 |
1 |
0 |
Efficiency |
>85 % |
60 - 85 % |
<60 % |
Lifespan |
>15 years |
5 - 15 years |
<5 years |
Investment Cost |
<1 M |
1 - 10 M |
>10 M |
Rupiah ENS |
Rp 0 |
Rp 0,- up to Rp 86.820.000,- |
> Rp 86.82 million,- |
Customer Satisfaction Level |
Nominal |
Voltage Drop Voltage |
Complaints |
Research Methods
The process of selecting mitigation options
using risk and cost-benefit analysis. The research started with collecting test
data, conducting a risk analysis, and analyzing
economic feasibility, and then a multi-criteria analysis was carried out.
The results of the calculation of the condition
of the 3 GI Angke power transformer after mitigation
were tested with the 5 criteria listed in the previous table. To determine the
weight of each criterion, a questionnaire was given to stakeholders and
experts. The average of the importance of each criterion is used as a tool to
obtain the most optimal mitigation action.
1.
Risk Analysis
Risks that may occur if
no mitigation measures are selected. The operation of the 3 GI Angke transformer without any repairs will make the
transformer prone to breakdown. The material risk is worth more than
6,000,000,000 rupiahs.
2.
Economic feasibility
analysis
Economic feasibility
analysis is carried out by calculating investment costs and rupiah ENS
3.
Investment Cost Calculation
for Replacement and Repair of Transformer #3 GI Angke
The budget plan is an
analysis carried out to interpret the costs that will be used to complete a
project. A review of the budget plan is carried out before the project is
implemented. How to calculate the costs that will be incurred to work on a
project according to the following equation:
RAB��������������������������������������������� =
Volume of work x Unit Price
RAB Transformer Replacement = IDR
11,829,649,850
RAB Transformer Repair
��� = IDR 268,094,603
4.
Rupiah ENS (Energy Not
Served)
ENS is the sum of MWh
that has not been distributed to customers for 1 year due to power supply
interruptions. ENS is calculated by:
ENS
= Σ[gangguan(MW)xdurasi(h)]
While AENS is the
average amount of energy that is not channelled into the distribution system in
1 year.
AENS
=
ENS data in this study
using transformer fault data in the Duri Kosambi ULTG area from 2019 to 2022. The selected ENS is
transformer fault due to equipment conditions. During the last 3 years,
transformers with less than 5 years of operation have never experienced
problems due to equipment conditions. Meanwhile, for transformers over 25 years
old, there has been 1-time fault due to damage to the control cable, which resulted
in a sudden pressure relay experiencing a short circuit.
The total ENS in the Duri Kosambi ULTG area in the
last 3 years for transformers aged over 25 years can be calculated:
ENS
= 0,42 MWh
AENS
=
Using the electricity selling price of rupiah
for over 25 years are:
Rupiah ENS = 0.14 MWh x Rp 1477,- = Rp
206.780,-
Table 4
Calculation Result of Power Transformer ENS
|
Transformer age < 5
years |
Transformer age >
25 years |
ENS |
0 |
0.42 MWh |
AENS |
0 |
0.14 MWh |
Rupiah ENS |
0 |
Rp 207.780,- |
Results and Discussion
The value of each mitigation option is shown in the following
table:
Table 5
Multi-Criteria Analysis Scoring Results
Criteria |
Weight |
Transformer replacement |
|
Transformer repairment |
|
Declaration % Transformer readiness |
23 |
Good (2) |
0.46 |
Medium (1) |
0.23 |
Lifespan |
22 |
Long (2) |
0.44 |
Short (0) |
0 |
Investment Cost |
17 |
Expensive (0) |
0 |
Cheap(2) |
0.34 |
Rupiah ENS |
17 |
Rp 0 (2) |
0.34 |
Rp 207,780(1) |
0.17 |
Customer Satisfaction
Level |
21 |
Satisfied (2) |
0.42 |
Satisfied (2) |
0.42 |
Total |
100 |
|
1.66 |
|
1.16 |
Based on the results of the multi-criteria
analysis in the table above, it can be seen that the transformer replacement
score is 1.66 while the transformer repair score is 1.16. Overall, power
transformer replacement is worth more engine efficiency and long service life.
The new power transformer will produce a higher efficiency than the repaired
old power transformer. Although transformer repairs require fewer investment
costs, both mitigation options have the same value in terms of Return on
Investment. From the two mitigation options, PT PLN (Persero) will get the
entire investment cost back in less than one year. By considering these values,
the conclusion that can be drawn is that for a 3 GI Angke
power transformer, the mitigation option of replacing a transformer is better
and more profitable than repairing a few components.
Conclusion
Multi-criteria analysis can help select more
profitable mitigation options for PT PLN (Persero). From the analysis that has
been carried out in considering the best mitigation options for the 3 GI Angke Transformer, the transformer replacement option is
superior, with a difference of 0.50 in value. An assessment using more complex
and varied data is needed to validate the multi-criteria analysis.
BIBLIOGRAPHY
Tryolinna,
A. (2019). Optimizing Stakeholder Management: Operational Decision Making for
Transformer Replacement. 2019 International Conference on High Voltage
Engineering and Power System.
Rifai, Deni F., Reza Asriandi E.,
Siti Rahma. �Analisis Multi
Kriteria Dalam Pengembangan Jalan Lintas Barat Sumatera (Studi Kasus: Kecamatan
Talang Padang, Provinsi
Lampung). 2021 Journal of Infrastructure Planning and Design vol 1.
Alijoyo,
A., Wijaya, B., Jacob, I. Analisis Keputusan Multikriteria. CRMS. Jakarta: Indonesia.
PT PLN (Persero). (2013). Director Decree No. 149/K.DIR/2013
about The Replacement Criteria of The Substation Equipment in PT PLN (Persero)
PT PLN (Persero). �Director Decree No. 520: Maintenance Guideline�.
Jakarta, 2014.
PT PLN (Persero) Unit Induk Transmisi Jawa Bagian Barat.
2021. Panduan Evaluasi Derating Trafo
& IBT. Jakarta,2021.
Mendoza, Guillermo A. 1999. Panduan Untuk Menerapkan
Analisis Multikriteria dalam Menilai Kriteria
dan Indikator. CIFOR. Jakarta: Indonesia.
Copyright holder: Imran Syahrizal, Budi Sudiarto (2022) |
First publication right: Syntax Literate: Jurnal Ilmiah Indonesia |
This article is licensed under: |