Syntax Literate: Jurnal Ilmiah Indonesia p�ISSN: 2541-0849 e-ISSN: 2548-1398

Vol. 7, No. 6, Juni 2022

 

RISK COST-BENEFIT ANALYSIS OF 3 GI ANGKE TRANSFORMERS TO ACHIEVE OPTIMAL MITIGATION

 

Imran Syahrizal, Budi Sudiarto

Engineering Faculty University of Indonesia Depok, Indonesia

Email: [email protected], [email protected]

 

Abstract 

The power transformer is one of the leading electrical instruments used to transmit electrical power between generators to adjust the voltage without changing its frequency. Like any other machine, the power transformer will experience degradation over time. High electrical resistance, external factors and environmental temperature could lead to faster degradation. This degradation usually affects transformer isolation material. Degradation of this component furthermore will decrease power transformer efficiency. In 2022, power transformer 3 GI Angke has been used for 28 years, while PT PLN (Persero) has decided that power transformers operating for over 25 years fall into the category of the old machine and need to be replaced. The last asset wellness maintenance data showed that ethane was found in the oil insulation in the second level inspection. The third level inspection also showed degradation of bushing insulation, with the tan delta test result showing the value of 1.28. Asset wellness management is needed in this situation to ensure stability. There are two mitigation options available, to replace some of the components or replace the power transformer altogether. Risk, cost and benefit analysis using a multicriteria approach is used in choosing the best mitigation approach for PT PLN (Persero).

 

Keywords: asset management, power transformer, multi-criteria analysis

 

Introduction

PT PLN (Persero) is responsible for supplying electricity for all customers. Electricity is generated from the generator through transmission and distribution lines so that customers can use the electricity. One of the vital components of the electricity distribution system is the power transformer. To maintain stable service, power transformers with an operating age of over 25 years are included in the old category according to PLN's SK DIR 149.

One of the transformers managed by PLN is transformer three at GI Angke. This transformer is 28 years old. Based on the last test results, an assessment of the Health Index of the transformer was carried out.

Determination of equipment health index using logic OR

 

 

 

Table 1. Classification Of 1,6, 9 For Each Inspection Item.

No

Sub System

Item Inspection

Test Result

Score Item Inspection

Score Subsystem

Score Health Index

1

Dielectric

DGA

548.21 (4)

1

1

 

2

Current Carrying unit

Tan Delta

1.63 %

1

1

1

3

Bushing

Tan Delta

1.38 %

1

1

 

 

Based on table 1, the health index of the 3 GI Angke transformer is 1. Moreover, the susceptibility of the 3 GI Angke transformer is determined using the data below.

 

Table 2

Susceptibility Simulation Scoring Results.

No

Parameter Susceptibility

Score

Index

Average

Susceptibility

1

Average loading (1 year)

79.6 %

6

 

 

 

 

28/5 =5.5

 

 

 

 

6

 

2

TFC

270100

6

3

Neutral

12 ohms

6

4

Life

>25

1

5

load type

Linear

9

 

Based on table 2, the susceptibility of the transformer 3 GI Angke = 6

 

Figure 1. The Risk Assessment Matrix

​​�����������

Following the health index score = 1 and the susceptibility score = 6, using the matrix above, the probability of failure 3 GI transformer Angke = DIn order to determine the priority of work, the probability of failure is combined with the GI criticality. Transformer #3 GI Angke has a criticality level of 4, so based on the matrix below, the priority of work on transformer #3 GI Angke is priority 1 (red).

 

Figure 2. Matrix For Determining The Priority

 

An old Power Transformer is very susceptible to failure due to a decrease in the quality of insulation or damage to its components. To minimize interference, the old transformer can be taken corrective action. Actions that can be taken care in the form of replacing a new transformer or repairing damaged components. Each mitigation action has its advantages and disadvantages. For this reason, it is necessary to analyze the costs/benefits and risks of the two mitigation action options. Limited resources and time owned by PT PLN (Persero) are essential considerations in determining mitigation actions with the most optimal benefits.

Cost analysis is related to the investment costs required in mitigation actions. Risk analysis includes the calculation of machine usability and customer satisfaction. In comparison, the benefit analysis calculates the efficiency of the machine and the company's profits. These three factors are summarized into the following 5 criteria, which are used as considerations in selecting mitigation actions, including:

1.     % Transformer Readiness

% transformer readiness is the percentage of transformer readiness in delivering electrical power to its nameplate capacity. A decrease in % transformer readiness occurs if the results of the transformer assessment show deterioration. The assessment parameters used in the loading reference are DGA test assessments, oil characteristics and electrical tests. In this journal, % transformer readiness is divided into 3 with the distribution of values:

2: declaration of % transformer readiness >90%

1: 80 % < declaration of % readiness transformer < 90%

0: declaration % transformer readiness < 80%

2.     Power Transformer Life

Transformer life is when the transformer can operate since it is first energized. The longer the transformer can operate, the better for PT PLN (Persero) due to the large investment costs for new transformer installations starting from the procurement of transformers until the transformer can finally be energized. Transformer life is grouped into 3 value categories:

2: lifetime >15 years

1: lifetime 5-15 years

0: lifetime <5 years

3.     Investment cost

The number of investment costs causes stakeholders to consider the available options in dealing with the case of a transformer that has deteriorated. This is important because PT PLN (Persero) manages GIs throughout Indonesia, where each GI has its transformer problem. Investment costs are also categorized into 3 value groups:

2: investment costs<1M

1: investment costs 1-10M

0: investment costs >10M

4.     Rupiah ENS (Energy Not Served)

The reliability of a transformer can be seen from the frequency and duration of the transformer experiencing disturbances. One of the indicators used is the ENS transformer. This ENS is used to determine the number of losses experienced by PT PLN (Persero) due to the transformer not operating due to interference. The amount of ENS rupiah is categorized into 3 values:

2: ENS Rupiah = IDR 0, -

1: ENS Rupiah = IDR 0, - to IDR 86, 820, 000, -

0: ENS Rupiah > 86, 820, 000, -

5.     Level of customer satisfaction

Apart from pursuing profit, PT PLN (Persero) as a BUMN must also pay attention to customer satisfaction. The level of customer satisfaction can be seen through the level of voltage and frequency that reaches the customer's house line, the number of power outages and customer complaint reports. The level of customer satisfaction is grouped into 3 values:

2: nominal voltage

1: voltage drop

0: complaints occur

 

Each value of the 5 criteria above is used to compare the two available mitigation actions.

Table 3

Criteria for comparing mitigation options

 

Value

Criterion

2

1

0

Efficiency

>85 %

60 - 85 %

<60 %

Lifespan

>15 years

5 - 15 years

<5 years

Investment Cost

<1 M

1 - 10 M

>10 M

Rupiah ENS

Rp 0

Rp 0,- up to

Rp 86.820.000,-

> Rp 86.82 million,-

Customer Satisfaction Level

Nominal

Voltage Drop Voltage

Complaints

 

Research Methods

The process of selecting mitigation options using risk and cost-benefit analysis. The research started with collecting test data, conducting a risk analysis, and analyzing economic feasibility, and then a multi-criteria analysis was carried out.

The results of the calculation of the condition of the 3 GI Angke power transformer after mitigation were tested with the 5 criteria listed in the previous table. To determine the weight of each criterion, a questionnaire was given to stakeholders and experts. The average of the importance of each criterion is used as a tool to obtain the most optimal mitigation action.

1.     Risk Analysis

Risks that may occur if no mitigation measures are selected. The operation of the 3 GI Angke transformer without any repairs will make the transformer prone to breakdown. The material risk is worth more than 6,000,000,000 rupiahs.

2.     Economic feasibility analysis

Economic feasibility analysis is carried out by calculating investment costs and rupiah ENS

3.     Investment Cost Calculation for Replacement and Repair of Transformer #3 GI Angke

The budget plan is an analysis carried out to interpret the costs that will be used to complete a project. A review of the budget plan is carried out before the project is implemented. How to calculate the costs that will be incurred to work on a project according to the following equation:

RAB��������������������������������������������� = Volume of work x Unit Price

RAB Transformer Replacement   = IDR 11,829,649,850

RAB Transformer Repair         ��� = IDR 268,094,603

4.     Rupiah ENS (Energy Not Served)

ENS is the sum of MWh that has not been distributed to customers for 1 year due to power supply interruptions. ENS is calculated by:

ENS = Σ[gangguan(MW)xdurasi(h)]

While AENS is the average amount of energy that is not channelled into the distribution system in 1 year.

AENS =

ENS data in this study using transformer fault data in the Duri Kosambi ULTG area from 2019 to 2022. The selected ENS is transformer fault due to equipment conditions. During the last 3 years, transformers with less than 5 years of operation have never experienced problems due to equipment conditions. Meanwhile, for transformers over 25 years old, there has been 1-time fault due to damage to the control cable, which resulted in a sudden pressure relay experiencing a short circuit.

The total ENS in the Duri Kosambi ULTG area in the last 3 years for transformers aged over 25 years can be calculated:

ENS = 0,42 MWh

AENS =

Using the electricity selling price of rupiah for over 25 years are:

Rupiah ENS = 0.14 MWh x Rp 1477,- = Rp 206.780,-

 

Table 4

Calculation Result of Power Transformer ENS

 

Transformer age < 5 years

Transformer age > 25 years

ENS

0

0.42 MWh

AENS

0

0.14 MWh

Rupiah ENS

0

Rp 207.780,-

 

Results and Discussion

The value of each mitigation option is shown in the following table:

 

Table 5

Multi-Criteria Analysis Scoring Results

Criteria

Weight

Transformer replacement

 

Transformer repairment

 

Declaration %

Transformer readiness

23

Good (2)

0.46

Medium (1)

0.23

Lifespan

22

Long (2)

0.44

Short (0)

0

Investment Cost

17

Expensive (0)

0

Cheap(2)

0.34

Rupiah ENS

17

Rp 0 (2)

0.34

Rp 207,780(1)

0.17

Customer Satisfaction Level

21

Satisfied (2)

0.42

Satisfied (2)

0.42

Total

100

 

1.66

 

1.16

 

Based on the results of the multi-criteria analysis in the table above, it can be seen that the transformer replacement score is 1.66 while the transformer repair score is 1.16. Overall, power transformer replacement is worth more engine efficiency and long service life. The new power transformer will produce a higher efficiency than the repaired old power transformer. Although transformer repairs require fewer investment costs, both mitigation options have the same value in terms of Return on Investment. From the two mitigation options, PT PLN (Persero) will get the entire investment cost back in less than one year. By considering these values, the conclusion that can be drawn is that for a 3 GI Angke power transformer, the mitigation option of replacing a transformer is better and more profitable than repairing a few components.

 

Conclusion

Multi-criteria analysis can help select more profitable mitigation options for PT PLN (Persero). From the analysis that has been carried out in considering the best mitigation options for the 3 GI Angke Transformer, the transformer replacement option is superior, with a difference of 0.50 in value. An assessment using more complex and varied data is needed to validate the multi-criteria analysis.

 

 


 

BIBLIOGRAPHY

 

Tryolinna, A. (2019). Optimizing Stakeholder Management: Operational Decision Making for Transformer Replacement. 2019 International Conference on High Voltage Engineering and Power System.

 

Rifai, Deni F., Reza Asriandi E., Siti Rahma. �Analisis Multi Kriteria Dalam Pengembangan Jalan Lintas Barat Sumatera (Studi Kasus: Kecamatan Talang Padang, Provinsi Lampung). 2021 Journal of Infrastructure Planning and Design vol 1.

 

Alijoyo, A., Wijaya, B., Jacob, I. Analisis Keputusan Multikriteria. CRMS. Jakarta: Indonesia.

 

PT PLN (Persero). (2013). Director Decree No. 149/K.DIR/2013 about The Replacement Criteria of The Substation Equipment in PT PLN (Persero)

 

PT PLN (Persero). �Director Decree No. 520: Maintenance Guideline�. Jakarta, 2014.

 

PT PLN (Persero) Unit Induk Transmisi Jawa Bagian Barat. 2021. Panduan Evaluasi Derating Trafo & IBT. Jakarta,2021.

 

Mendoza, Guillermo A. 1999. Panduan Untuk Menerapkan Analisis Multikriteria dalam Menilai Kriteria dan Indikator. CIFOR. Jakarta: Indonesia.

 

Copyright holder:

Imran Syahrizal, Budi Sudiarto (2022)

 

First publication right:

Syntax Literate: Jurnal Ilmiah Indonesia

 

This article is licensed under: